Planline › Guides › Earned value management

Earned value management explained

Earned value answers two questions with three numbers: are we ahead or behind, and are we spending more or less than planned for the work done? This guide explains every formula with one worked example in man-hours.

Open the free schedulerNo sign-up needed, nothing to install. Your data stays on your device.

The three base numbers

TermAlso calledMeaning
PV planned valueBCWSThe budget for the work that should be done by the status date
EV earned valueBCWPThe budget for the work actually done by the status date
AC actual costACWPWhat the work done actually cost (or the man-hours actually spent)
BAC budget at completionThe total budget for all the work

The trick is in EV: it values the work done at its budget, not at what it cost. That makes it comparable with both the plan (PV) and the spend (AC).

Man-hours or money?

On construction projects earned value is very often measured in man-hours rather than currency. Budgeted man-hours come from quantities and norms, earned man-hours come from quantities installed, and actual man-hours come from timesheets. This keeps craft productivity separate from price changes in materials and exchange rates. The formulas are identical either way.

Worked example

A piping and steel package has a budget of 10,000 man-hours. At the status date:

MeasureFormulaResultReading
Schedule variance (SV)EV − PV−750 MHBehind plan
Schedule performance index (SPI)EV ÷ PV0.8585% of planned work done
Cost variance (CV)EV − AC−850 MHOverspent
Cost performance index (CPI)EV ÷ AC0.83Each hour spent earns 0.83 hours of budget
Estimate at completion (EAC)BAC ÷ CPI12,000 MHForecast if productivity stays the same
Estimate to complete (ETC)EAC − AC6,900 MHHours still needed
Variance at completion (VAC)BAC − EAC−2,000 MHForecast overrun
To-complete performance index (TCPI)(BAC − EV) ÷ (BAC − AC)1.17Productivity needed on the rest to finish on budget

Reading it together: the package is about 15% behind and 17% less productive than estimated. To finish within 10,000 hours the crews would need to work 17% better than budget on the remaining work, which is rarely realistic, so the honest forecast is around 12,000 hours.

Which EAC formula to use

Reading SPI with care

SPI is measured in budget, not in time, and it always returns to 1.0 at the end of a project because all the planned work is eventually earned. Late in a project it stops being a good schedule indicator; look at the critical path and float instead. A high SPI can also hide trouble if crews are doing easy, non-critical work ahead of plan while critical work slips.

What makes earned value reliable

Earned value in Planline

Planline calculates budget man-hours from quantities and norms, earned man-hours from the quantities you record, and the planned percent complete at the status date. The dashboard shows actual against planned progress, earned man-hours, the schedule performance index (SPI) and the planned versus actual S-curve. Actual hours from timesheets are not tracked in the scheduler, so calculate CPI and the forecast alongside it in the Excel report.

Frequently asked questions

What is a good SPI or CPI?

Exactly 1.0 means on plan. Above 1.0 is ahead of schedule (SPI) or under budget (CPI); below 1.0 is behind or over. Most owners start asking questions below about 0.95.

What is the difference between earned value and physical progress?

Physical progress is earned value expressed as a percentage: EV divided by BAC. Earned value management adds the comparison with planned value and actual cost.

Can I use earned value without cost data?

Yes. Using man-hours for PV, EV and AC is common in construction and gives the same indices without needing cost information.

Related guides

Try it on your own schedule

Planline is free and needs no sign-up. Your schedules stay in your browser unless you choose to sign in and save them to your account. Start a blank project, import your own file, or look around the example project first.

Open the free scheduler