Planline › Guides › Rules of credit

Rules of credit for progress measurement

Rules of credit decide how much progress a team earns for each step of an activity, so that "40% complete" means the same thing to the contractor, the client and the planner. Here are the measurement methods and example credit steps by discipline.

Open the free schedulerNo sign-up needed, nothing to install. Your data stays on your device.

Why rules of credit matter

Without agreed rules, percent complete becomes an opinion. A supervisor may report a pipe spool as 80% complete because it is hanging in place, while the client sees an unwelded, untested line. Rules of credit fix this by splitting each type of work into measurable steps, each with a fixed share of the activity's weight. They are normally written into the project's progress measurement procedure and agreed with the client before work starts.

Measurement methods

MethodHow progress is earnedGood for
Units completedQuantity done ÷ scope quantityRepetitive work: welds, cable metres, cubic metres of concrete
Weighted steps (milestones)Fixed percentage when each step is finishedWork with distinct stages: equipment, piping systems, drawings
0/100Nothing until completeVery short activities, under one reporting period
50/50Half at start, half at finishShort activities spanning two periods
Level of effortProgress follows elapsed timeSupport work: supervision, project management
Supervisor's estimateJudgementLast resort, small items only

Example credit steps by discipline

Examples only. These splits are typical of what appears in progress measurement procedures, but every project agrees its own. Use your contract's procedure where one exists.

Civil: concrete foundations

StepCredit
Excavation and blinding10%
Formwork20%
Reinforcement and embedded items25%
Concrete poured35%
Strip, cure and backfill10%

Structural steel (per tonne)

StepCredit
Shake-out and pre-assembly10%
Erected50%
Aligned and plumbed15%
Bolted up and torqued20%
Touch-up painting and punch list5%

Piping (per test pack or line, weighted by inch-dia)

StepCredit
Spools erected in position30%
Field joints welded (by inch-dia)40%
Supports installed10%
NDT complete and accepted5%
Hydrotest passed10%
Reinstatement5%

Mechanical equipment

StepCredit
Set on foundation50%
Levelled and aligned20%
Grouted10%
Internals and dressing10%
Final alignment and box-up10%

Electrical: cables

StepCredit
Cable pulled and dressed60%
Glanded and terminated (both ends)30%
Tested (insulation resistance, continuity)10%

Instrumentation

StepCredit
Calibrated10%
Installed and supported35%
Hook-up (process and air)30%
Loop checked25%

Engineering deliverables (drawings, documents)

StepCredit
Started10%
Internal check complete40%
Issued for review (IFR)60%
Client comments incorporated, issued for approval (IFA)80%
Issued for construction (IFC)100%

Worked example

A piping test pack has 600 inch-dia of field welds and a budget of 1,500 man-hours. Spools are all erected, 300 of 600 inch-dia are welded, and half the supports are in.

Progress = 30% (spools) + 40% × 300/600 (welds) + 10% × 0.5 (supports) = 30 + 20 + 5 = 55%, so the test pack has earned 0.55 × 1,500 = 825 man-hours.

Tips

Applying rules of credit in Planline

Either split the work into one activity per step with the step's share of man-hours, which gives the clearest Gantt chart, or keep one activity and record the credited quantity in the Progress entry sheet (in the example above, 55% of the scope quantity). Planline then calculates earned man-hours and the weighted overall progress.

Frequently asked questions

Who sets the rules of credit?

Normally the contractor proposes them in the progress measurement procedure and the client approves them before construction starts. Owners often have standard rules they require.

Should engineering progress use rules of credit?

Yes. Weighted steps tied to document issues (IFR, IFA, IFC) are the standard way to measure engineering progress objectively.

What is the difference between rules of credit and weightage?

Weightage sets how much each activity counts in the overall progress. Rules of credit set how much progress an activity earns for each step within it.

Related guides

Try it on your own schedule

Planline is free and needs no sign-up. Your schedules stay in your browser unless you choose to sign in and save them to your account. Start a blank project, import your own file, or look around the example project first.

Open the free scheduler