Planline › Guides › Three-week look-ahead schedule

How to make a three-week look-ahead schedule

The master schedule says what should happen this quarter. The look-ahead says what the crews will actually do in the next three weeks, and checks that nothing will stop them. Here is how to run one on a construction site.

Open the free schedulerNo sign-up needed, nothing to install. Your data stays on your device.

What a look-ahead is

A look-ahead schedule is a short window, usually two to six weeks with three the most common, taken from the master schedule and broken into more detail. It is a working tool for site supervisors: it lists the work planned for each crew, day by day or week by week, and confirms that everything needed for that work will be ready.

It is not a separate plan. Dates come from the master schedule; the look-ahead adds detail and exposes problems early enough to fix them.

Build it in five steps

  1. Filter the master schedule. Take every activity that is in progress or due to start in the window, plus anything critical or near-critical starting just after it.
  2. Break activities down. A master activity such as "Area 200 piping erection, 4 weeks" becomes daily or weekly tasks by line, test pack or crew.
  3. Check constraints. For each task, confirm the items in the checklist below. Anything not ready gets an owner and a date.
  4. Assign crews. Match each task to a named supervisor and crew size, and check the total against manpower on site.
  5. Review weekly. Each week, drop the past week, add a new third week, record what was done and why anything was missed.

Constraint checklist

Work only goes into the "will do" list when every constraint is cleared:

Example look-ahead

TaskCrewWeek 1Week 2Week 3ConstraintOwner
Erect rack steel, bays 1 to 6Steel A (8)■■■■■■■Clear
Set pumps P-201 A/BMech (6)■■■Grout cure sign-offCivil supervisor
Erect spools, lines 201 to 214Piping B (10)■■■■■■■■■Spools 207, 211 not deliveredMaterials controller
Hydrotest test pack TP-14Test crew (4)■■NDT results pendingQC inspector
Pull cables, rack tray level 2Elec (8)■■■■■■■■■■■■■Clear

Measure the plan: percent plan complete

At the end of each week, count the tasks committed for that week and the tasks actually completed. Percent plan complete (PPC) is completed ÷ committed. A site that consistently reaches 80% or more has a reliable short-term plan; lower figures point to constraints not being cleared. Record the reason for every miss (materials, drawings, weather, manpower, previous work late) and look at the totals each month: the most common reason is where the fix is.

Common mistakes

Using Planline for look-aheads

Keep the master schedule in Planline and record progress at each status date, so the remaining dates are always current. Export the schedule to Excel and filter on start and finish dates to pull the window for the coming weeks, then add your crew and constraint columns. The Gantt chart's week zoom gives a quick visual check of what is starting.

Frequently asked questions

Why three weeks?

Three weeks is long enough to deliver missing materials, drawings or permits once a constraint is spotted, and short enough for the detail to be accurate. Shutdowns often use daily or shift-level look-aheads instead.

Who prepares the look-ahead?

Usually the area or discipline supervisors with the site planner. The planner extracts the window from the master schedule; supervisors break it down and confirm constraints.

What is a good PPC?

Around 80% or higher is generally considered a reliable short-term plan. More important than the figure is tracking why tasks are missed and fixing the common causes.