Work breakdown structure for EPC projects

The WBS is the backbone of the schedule, the estimate and the progress report. Here is how to structure one for an engineering, procurement and construction project, with a complete example you can copy.

Open the free schedulerNo sign-up needed, nothing to install. Your data stays on your device.

What a WBS is for

A work breakdown structure divides the whole scope into smaller, manageable parts arranged in a hierarchy. On an EPC project the same structure is used to schedule the work, roll up man-hours and cost, measure progress and report to the client. If the WBS is wrong, every report built on it is awkward for the rest of the project, so it is worth an afternoon of thought.

Four rules that keep a WBS sound

  1. The 100% rule. The children of any element add up to exactly the whole of that element: no gaps, no extras.
  2. Mutually exclusive. Each piece of work sits in one place only, so man-hours are never counted twice.
  3. Outcome-oriented. Elements describe deliverables or physical results (Area 200 piping) rather than actions (welding).
  4. Fit for reporting. The levels match how the client and management want to see progress, usually by phase, area and discipline.

Phase first or area first?

Most EPC schedules use a hybrid. Engineering and procurement are organised by discipline and package, because that is how design teams and buyers work. Construction is organised by area or unit, then discipline, because crews move from area to area. Commissioning is organised by system, because systems cross area boundaries: a cooling water system runs through several plots.

LayoutWorks well forWatch out for
Phase › discipline › areaEngineering-heavy projects, small sitesConstruction progress by area is hard to read
Area › phase › disciplineLarge sites with separate contractors per areaEngineering deliverables often serve several areas
Hybrid (shown below)Most EPC and EPCM projectsNeeds clear coding so reports can still filter by discipline

Example: gas processing plant expansion

Activities sit under the lowest level. For example, under 1.4.2.4 Piping you would find "Erect large-bore spools", "Field welding", "Install supports", "Hydrotest test packs" and "Reinstatement", each with a quantity and a norm.

How deep should it go?

Stop breaking down when an element is small enough to estimate with confidence, assign to one party, and report on. On most EPC projects that means four or five levels above the activities. Going deeper makes the WBS a list of activities in disguise, which is harder to maintain and adds nothing to reports.

Coding

Give every element a code that shows its position, such as 1.4.2.4. Keep the codes stable once reporting starts: clients often map their cost and progress systems to them. If you also need to report by discipline across all areas, keep the discipline at the same level in every branch (in the example above it is always the fourth level under construction), or add a separate discipline code to each activity.

WBS, OBS and CBS

The point where a WBS element meets one responsible party is called a control account. It is where budget, schedule and progress are managed together, and where earned value is usually measured.

Common mistakes

Building the WBS in Planline

Type the elements as rows, then use indent and outdent to make the hierarchy; summary rows roll up dates, man-hours and progress automatically, and WBS codes are generated from the outline. You can also paste an existing WBS from Excel: Planline works out the levels from outline numbers, indentation or WBS codes.

Frequently asked questions

How many levels should a WBS have?

For most EPC projects four or five levels above the activities: project, phase, area or package, discipline, and sometimes a sub-area. Stop when an element can be estimated, assigned and reported on its own.

Is the WBS the same as the activity list?

No. The WBS is the hierarchy of deliverables and areas. Activities are the work steps that sit under its lowest level.

Should commissioning follow areas or systems?

Systems. Commissioning hands over complete systems, which usually cross area boundaries, so a system-based structure matches how the work is accepted.